Micropile installation work has been completed.

Starting August 24th, 2017, Frank Coluccio Construction will begin installation of the above ground storage tank and air release valve vault in the pump station property.  Normal working hours are 8:30 am to 5:00 pm, Monday through Friday.  In addition, work will be performed on Saturday, August 26th, and Saturday, September 2nd, from 9:00 am to 6:00 pm.  The contractor is choosing to work on Saturdays to expedite the schedule with the aim to complete construction by late September, 2017.